SUMMARY OF WATER SPILLED OVER SPILLWAY For Yr 2017
Month | Year-2017 | Remark | |||
Duration | Spilled over | ||||
Hour | m3/s | Mm3 | Ac-ft | ||
August | 206.67 | 199.02 | 148.07 | 120,045 | |
September | 263.66 | 286.766 | 272.19 | 220,669 | Up to 20.9.2017 |
October | |||||
November | |||||
December | |||||
Total | 470.33 | 248.366 | 420.2646731 | 340714.6229 | 0 |
Note: 1 Acre-ft = 1233.48m3
- In 2017, Flood being started on August 23rd.
- Total spilled volume over Spillway is 420.26 Mm3 (721761 ac-ft) from 23rd August to 20th September.
- Total loss of energy is about 67 Million kWh and loss of revenue is about 4.7 Billions Kyat from 23rd August to 20th September.
Gold Energy Company Limited
Thaukyegat(2) Hydropower Project
Summary of water spilled over spillway
Sr No | Date | Spilled Water | Loss of Energy (M.kWh) |
Loss of Revenue (M.ks) |
||
m3 | Ac-ft | Mm3 | ||||
1 | August ^ 2017 23.8.2017 |
4,684,635 | 3,797.90 | 4.68 | 0.75 | 52.20 |
2 | 24.8.2017 | 12,699,072 | 10,295.32 | 12.70 | 2.02 | 141.51 |
3 | 25.8.2017 | 8,087,010 | 6,556.26 | 8.09 | 1.29 | 90.12 |
4 | 26.8.2017 | 19,317,312 | 15,660.82 | 19.32 | 3.08 | 215.26 |
5 | 27.8.2017 | 17,308,512 | 14,032.26 | 17.31 | 2.76 | 192.88 |
6 | 28.8.2017 | 18,567,360 | 15,052.83 | 18.57 | 2.96 | 206.91 |
7 | 29.8.2017 | 17,368,992 | 14,081.29 | 17.37 | 2.77 | 193.55 |
8 | 30.8.2017 | 14,271,552 | 11,570.15 | 14.27 | 2.27 | 159.04 |
9 | 31.8.2017 | 35,767,872 | 28,997.53 | 35.77 | 5.69 | 398.58 |
Total | 148,072,317 | 120,044.36 | 148.07 | 23.57 | 1,650.05 | |
10 | September ^ 2017 1.9.2017 |
22,070,000 | 17,892.47 | 22.07 | 3.51 | 245.94 |
11 | 2.9.2017 | 27,520,000 | 22,310.86 | 27.52 | 4.38 | 306.67 |
12 | 3.9.2017 | 20,780,000 | 16,846.65 | 20.78 | 3.31 | 231.56 |
13 | 4.9.2017 | 14,950,000 | 12,120.18 | 14.95 | 2.38 | 166.60 |
14 | 5.9.2017 | 9,760,000 | 7,912.57 | 9.76 | 1.55 | 108.76 |
15 | 6.9.2017 | 19,760,000 | 16,019.72 | 19.76 | 3.15 | 220.20 |
16 | 7.9.2017 | 9,620,000 | 7,799.07 | 9.62 | 1.53 | 107.20 |
17 | 8.9.2017 | 21,610,000 | 17,519.54 | 21.61 | 3.44 | 240.81 |
18 | 9.9.2017 | 20,750,000 | 16,822.32 | 20.75 | 3.30 | 231.23 |
19 | 10.9.2017 | 14,450,000 | 11,714.82 | 14.45 | 2.30 | 161.02 |
20 | 11.9.2017 | 7,430,000 | 6,023.61 | 7.43 | 1.18 | 82.80 |
21 | 12.9.2017 | 14,810,000 | 12,006.68 | 14.81 | 2.36 | 165.04 |
22 | 13.9.2017 | 1,770,000 | 1,434.96 | 1.77 | 0.28 | 19.72 |
23 | 14.9.2017 | 10,350,000 | 8,390.89 | 10.35 | 1.65 | 115.34 |
24 | 15.9.2017 | 6,390,000 | 5,180.47 | 6.39 | 1.02 | 71.21 |
25 | 16.9.2017 | 12,030,000 | 9,752.89 | 12.03 | 1.92 | 134.06 |
26 | 17.9.2017 | 15,680,000 | 12,712.00 | 15.68 | 2.50 | 174.73 |
27 | 18.9.2017 | 8,930,000 | 7,239.68 | 8.93 | 1.42 | 99.51 |
28 | 19.9.2017 | 7,560,000 | 6,129.00 | 7.56 | 1.20 | 84.25 |
29 | 20.9.2017 | 5,970,000 | 4,839.96 | 5.97 | 0.95 | 66.53 |
Total | 272,190,000 | 220,668.35 | 272.19 | 43.33 | 3,033.16 | |
Grand Total | 420,262,317 | 340,712.71 | 420.26 | 66.90 | 4,683.21 |
Water Spilled Over Spillway on 23rd August
Water Spilled Over Spillway on 24th August
Water Spilled Over Spillway on 25th August
Water Spilled Over Spillway on 31st August
Water Spilled Over Spillway on 7th September
Water Spilled Over Spillway on 11th September
Water Spilled Over Spillway on 12th September
Water Spilled Over Spillway on 13th And 14th September
Water Spilled Over Spillway on 15th And 16th September
Water Spilled Over Spillway on 17th And 18th September
Water Spilled Over Spillway on 19th And 20th September
SUMMARY OF WATER SPILLED OVER SPILLWAY FOR Ys 2013 To Ys 2015
Month | Year-2013 | Year-2014 | Year-2015 | |||||||||
Duration | Spilled over | Duration | Spilled over | Duration | Spilled over | |||||||
Hour | m3/s | Mm3 | Ac-ft | Hour | m3/s | Mm3 | Ac-ft | Hour | m3/s | Mm3 | Ac-ft | |
August | 356 | 282.71 | 362.56 | 293,933 | 236.5 | 202.91 | 172.26 | 139,654 | 448.08 | 240.47 | 387.9 | 314,476 |
September | 359 | 154.99 | 200.13 | 162,248 | 213.37 | 147.87 | 113.58 | 92,081 | 22.83 | 137.79 | 11.33 | 9,185 |
October | 200 | 224.54 | 161.7 | 131,093 | ||||||||
November | 317 | 131.86 | 150.56 | 122,061 | ||||||||
December | 35 | 120.86 | 15.34 | 12,436 | ||||||||
Total | 1267 | 182.99 | 890.29 | 721,771 | 449.87 | 176.81 | 285.84 | 231734.6 | 470.91 | 235.49 | 399.23 | 323661.51 |
Note: 1 Acre-ft = 1233.48m3
- In 2013, Flood started on August 18th and ended on December 15th in total duration of 1267 hours with average discharge 182.99m3/s. In 2013, Flood started on August 18th and ended on December 15th in total duration of 1267 hours with average discharge 182.99m3/s. Total spilled volume over Spillway was 890.28 Mm3 (721761 ac-ft). Total loss of energy is about 142 Millions kWh and loss of revenue is about 9.94 Billions Kyat.
- In 2014, Flood started on August 16th and ended on September 20th in total duration of 449.87 hours with average discharge 176.81m3/s. Total spilled volume over Spillway was 285.84 Mm3 (231735 ac-ft). Total loss of energy is about 46 Million kWh and loss of revenue is about 3.22 Billions Kyat.
- In 2015, Flood started on August 1st and ended on September 7th in total duration of 470.91 hours with average discharge 235.49m3/s. Total spilled volume over Spillway was 399.23 Mm3 (323662 ac-ft). Total loss of energy is about 64 Million kWh and loss of revenue is about 4.48 Billions Kyat.
- In 2016, no flood.